Construction is well underway for the Changing Lives Center!
Exterior Landscaping to the entire Changing Lives Center is complete
Administration and Programs Building is 90% completed with kitchen equipment ready to be installed
Chapel is 80% completed with ceiling and woodwork being finished. Stained glass will be installed mid March
Children’s Center is 80% completed with the elevator being installed in late February
We are excited to be currently digging the footings for 3 of the 4 apartment buildings with the walls and roof to be up within the next 4 months!
We are projecting opening our doors for women and children in mid 2010.
Please continue to keep this project in your prayers – especially for the protection of the women and children who are so desperately in need of the services the Center will provide – and keep checking back for updated progress from the construction site.
Click the arrow above or visit our Flickr site for the most current photos of construction.